First floor is up!

October 26, 2018

Steel Being Erected

October 8, 2018

Site Ready for Steel

September 18, 2018

Basement & Plumbling Completed

August 29, 2018

Basement Walls Completed

July 31, 2018

Majority of Basement Walls Complete

July 12, 2018

Ready to pour concrete for the basement walls.

June 21, 2018

Footings Complete

June 6, 2018

Ready to pour footings

May 29, 2018

Excavation Complete!

May 15, 2018

All ready for footings!

 

 